六类布线标准内容
 
The Specification of Field Test Requirements
for a Balanced Twisted-Pair Cabling System
 
I. Cat 6 Installation: field test requirements upon completion of the installation
 
A. General Requirements
1. Every cabling link in the installation shall be tested in accordance with the field test specifications defined in the most recent draft of the “Transmission Performance Specifications for 4-pair 100 ? Category 6 Cabling” under development by the Telecommunications Industry Association (TIA). At the time of this writing, PN-3727 TIA/EIA Draft Standard – Draft 7, dated August 23, 2000 represents the most recent version. This document will be referred to as the “TIA Cat 6 Draft Standard.”
2. The installed twisted-pair horizontal links shall be tested from the IDF in the telecommunications room to the telecommunication wall outlet in the work area against the “Permanent Link ” performance limits specification as defined in the TIA Cat 6 Draft Standard.
3. 100% of the installed cabling links must be tested and must pass the requirements of the standards mentioned in I.A.2 above and as further detailed in Section I.B. Any failing link must be diagnosed and corrected. The corrective action shall be followed with a new test to prove that the corrected link meets the performance requirements. The final and passing result of the tests for all links shall be provided in the test results documentation in accordance with Section I.C below.
4. Trained technicians who have successfully attended an appropriate training program and have obtained a certificate as proof thereof shall execute the tests. Appropriate training programs include but are not limited to installation certification programs provided by BiCSi or the ACP (Association of Cabling Professionals).
5. The test equipment (tester) shall comply with the accuracy requirements for the proposed level III field testers as defined in the TIA Cat 6 Draft Document. The tester including the appropriate interface adapter must meet the specified accuracy requirements. The accuracy requirements for the permanent link test configuration (baseline accuracy plus adapter contribution) are specified in Table B.2 of Annex B of the TIA Cat 6 Draft Standard. (Table B.3 in this TIA document specifies the accuracy requirements for the Channel configuration.)
6. The tester shall be within the calibration period recommended by the vendor in order to achieve the vendor-specified measurement accuracy.
7. The tester interface adapters must be of high quality and the cable shall not show any twisting or kinking resulting from coiling and storing of the tester interface adapters. In order to deliver optimum accuracy, preference is given to a permanent link interface adapter for the tester that can be calibrated to extend the reference plane of the Return Loss measurement to the permanent link interface. The contractor shall provide proof that the interface has been calibrated within the period recommended by the vendor. To ensure that normal handling on the job does not cause measurable Return Loss change, the adapter cord cable shall not be of twisted-pair construction.
8. The Pass or Fail condition for the link-under-test is determined by the results of the required individual tests (detailed in Section I.B). Any Fail or Fail* result yields a Fail for the link-under-test. In order to achieve an overall Pass condition, the results for each individual test parameter must Pass or Pass*.
9. A Pass or Fail result for each parameter is determined by comparing the measured values with the specified test limits for that parameter. The test result of a parameter shall be marked with an asterisk (*) when the result is closer to the test limit than the accuracy of the field tester. The field tester manufacturer must provide documentation as an aid to interpret results marked with asterisks.
 
Optional Requirements:
10. A representative of the end-user shall be invited to witness field testing. The representative shall be notified of the start date of the testing phase 5 business days before testing commences.
11. A representative of the end-user will select a random sample of 5% of the installed links. The representative (or his authorized delegate) shall test these randomly selected links and the results are to be stored in accordance with the prescriptions in Section I.C. The results obtained shall be compared to the data provided by the installation contractor. If more than 2% of the sample results differ in terms of the pass/fail determination, the installation contractor under supervision of the end-user representative shall repeat 100% testing and the cost shall be borne by the installation contractor.
 
B. Performance Test Parameters
 
The test parameters for Cat 6 are defined in TIA Cat 6 Draft standard, which refers to the TIA/EIA-568-B.2
standard. The test of each link shall contain all of the following parameters as detailed below. In order to pass the test all measurements (at each frequency in the range from 1 MHz through 250 MHz) must meet or exceed the limit value determined in the above-mentioned draft standard.
[Optional Requirement – can only be combined with option (a) in Section I.C.6.] Each parameter shall be measured from 1 through 350 MHz and all of these measurement points are to recorded in the test results information as detailed in Section I.C.6.
1. Wire Map
Wire Map shall report Pass if the wiring of each wire-pair from end to end is determined to be correct.
The Wire Map results shall include the continuity of the shield connection if present.
2. Length
The field tester shall be capable of measuring length of all pairs of a basic link or channel based on the propagation delay measurement and the average value for NVP ( 1 ). The physical length of the link shall be calculated using the pair with the shortest electrical delay. This length figure shall be reported and shall be used for making the Pass/Fail decision. The Pass/Fail criteria are based on the maximum length allowed for the Permanent Link configuration (90 meters – 295 feet) plus 10% to allow for the variation and uncertainty of NVP.
3. Insertion Loss (Attenuation)
Insertion Loss is a measure of signal loss in the permanent link or channel. The term “Attenuation” has
been used to designate “Insertion Loss.” Insertion Loss shall be tested from 1 MHz through 250 MHz in
maximum step size of 1 MHz. It is preferred to measure insertion loss at the same frequency intervals as NEXT Loss in order to provide a more accurate calculation of the Attenuation-to-Crosstalk ratio (ACR) parameter.
Minimum test results documentation (summary results): Identify the worst wire pair (1 of 4 possible).
The test results for the worst wire pair must show the highest attenuation value measured (worst case), the frequency at which this worst case value occurs, and the test limit value at this frequency
4. NEXT Loss
Pair-to-pair near-end crosstalk loss (abbreviated as NEXT Loss) shall be tested for each wire pair combination from each end of the link (a total of 12 pair combinations). This parameter is to be measured from 1 through 250 MHz. NEXT Loss measures the crosstalk disturbance on a wire pair at the end from which the disturbance signal is transmitted (near-end) on the disturbing pair. The maximum step size for NEXT Loss measurements shall not exceed the maximum step size defined in the draft standard as shown in Table 1, column 2.
Minimum test results documentation (summary results): Identify the wire pair combination that exhibits the worst case NEXT margin ( 2 ) and the wire pair combination that exhibits the worst value of NEXT (worst case). NEXT is to be measured from each end of the link-under-test. These wire pair combinations must be identified for the tests performed from each end. Each reported case shall include the frequency at which it occurs as well as the test limit value at this frequency.
Frequency Range (MHz) Maximum Step size (MHz)
1 – 31.25 0.15
31.26 – 100 0.25
100 – 250 0.50
250 – 350
5.
 
PSNEXT Loss
Power Sum NEXT Loss shall be evaluated and reported for each wire pair from both ends of the link-under- test (a total of 8 results). PSNEXT Loss captures the combined near-end crosstalk effect (statistical) on a wire pair when all other pairs actively transmit signals. Like NEXT this test parameter must be evaluated from 1 through 250 MHz and the step size may not exceed the maximum step size defined in the draft standard as shown in Table 1, column 2.
Minimum test results documentation (summary results): Identify the wire pair that exhibits the worst case margin and the wire pair that exhibits the worst value for PSNEXT. These wire pairs must be identified for the tests performed from each end. Each reported case shall include the frequency at which it occurs as well as the test limit value at this frequency.
6. ELFEXT Loss, pair-to-pair
Pair-to-pair FEXT Loss shall be measured for each wire-pair combination from both ends of the link-under-test. FEXT Loss measures the crosstalk disturbance on a wire pair at the opposite end (far-end) from which the transmitter emits the disturbing signal on the disturbing pair. FEXT is measured to compute ELFEXT Loss that must be evaluated and reported in the test results. ELFEXT measures the relative strength of the far-end crosstalk disturbance relative to the attenuated signal that arrives at the end of the link. This test yields 24 wire pair combinations. ELFEXT is to be measured from 1 through 250 MHz and the maximum step size for FEXT Loss measurements shall not exceed the maximum step size defined in the draft standard as in Table 1, column 2.
Minimum test results documentation (summary results): Identify the wire pair combination that exhibits the worst case margin and the wire pair combination that exhibits the worst value for ELFEXT. These wire pairs must be identified for the tests performed from each end. Each reported case shall include the frequency at which it occurs as well as the test limit value at this frequency.
7. PSELFEXT Loss
Power Sum ELFEXT is a calculated parameter that combines the effect of the FEXT disturbance from three wire pairs on the fourth one. This test yields 8 wire-pair combinations. Each wire-pair is evaluated from 1 through 250 MHz in frequency increments that do not exceed the maximum step size defined in the draft standard as shown in Table 1, column 2.
Minimum test results documentation (summary results): Identify the wire pair that exhibits the worst case margin and the wire pair that exhibits the worst value for PSELFEXT. These wire pairs must be identified for the tests performed from each end. Each reported case shall include the frequency at which it occurs as well as the test limit value at this frequency
8. Return Loss
Return Loss (RL) measures the total energy reflected on each wire pair. Return Loss is to be measured from both ends of the link-under-test for each wire pair. This parameter is also to be measured form 1 through 250 MHz in frequency increments that do not exceed the maximum step size defined in the draft standard as shown in Table 1, column 2.
Minimum test results documentation (summary results): Identify the wire pair that exhibits the worst case margin and the wire pair that exhibits the worst value for Return Loss. These wire pairs must be identified for the tests performed from each end. Each reported case shall include the frequency at which it occurs as well as the test limit value at this frequency.
9. ACR (Attenuation to crosstalk ratio) [This parameter is not demanded by the draft standard but may be
required in order to obtain the premise wiring manufacturer’s warranty]
ACR provides an indication of bandwidth for the two wire-pair network applications. ACR is a computed parameter that is analogous to ELFEXT and expresses the signal to noise ratio for a two wire-pair system. This calculation yields 12 combinations – six from each end of the link.
Minimum test results documentation (summary results): Identify the wire pair combination that exhibits the worst case margin and the wire pair combination that exhibits the worst value for ACR. These wire pair ombinations must be identified for the tests performed from each end. Each reported case shall include the frequency at which it occurs as well as the test limit value at this frequency.
10. PSACR [This parameter is not required by the draft standard but may be required in order to obtain the
premise wiring vendor's warranty]
The Power Sum version of ACR is based on PSNEXT and takes into account the combined NEXT disturbance of all adjacent wire pairs on each individual pair. This calculation yields 8 combinations - one for each wire pair from both ends of the link.
Minimum test results documentation (summary results): Identify the wire pair that exhibits the worst case margin and the wire pair that exhibits the worst value for PSACR. These wire pairs must be identified for the tests performed from each end. Each reported case shall include the frequency at which it occurs as well as the test limit value at this frequency.
11. Propagation Delay
Propagation delay is the time required for the signal to travel from one of the link to the other. This
measurement is to be performed for each of the four wire pairs.
Minimum test results documentation (summary results): Identify the wire pair with the worst case
propagation delay. The report shall include the propagation delay value measured as well as the test
limit value.
12. Delay Skew [as defined in TIA/EIA-568-B.1; Section 11.2.4.11]
This parameter shows the difference in propagation delay between the four wire pairs. The pair with the shortest propagation delay is the reference pair with a delay skew value of zero.
Minimum test results documentation (summary results): Identify the wire pair with the worst case propagation delay (the longest propagation delay). The report shall include the delay skew value measured as well as the test limit value.
 
C. Test Result Documentation
1. The test results information for each link shall be recorded in the memory of the field tester upon completion of the test.
2. The test results records saved by the tester shall be transferred into a Windows-based database utility that allows for the maintenance, inspection and archiving of these test records. A guarantee must be made that the measurement results are transferred to the PC unaltered, i.e., “as saved in the tester”at the end of each test and that these results cannot be modified at a later time. Superior protection in this regard is offered by testers that transfer the numeric measurement data from the tester to the PC in a non-printable format.
3. The database for the completed job shall be stored and delivered on CD-ROM including the software tools required to view, inspect, and print any selection of test reports.
4. A paper copy of the test results shall be provided that lists all the links that have been tested with the
following summary information
 
a) The identification of the link in accordance with the naming convention defined in the overall system documentation
b) The overall Pass/Fail evaluation of the link-under-test including the NEXT Headroom (overall worst case) number
c) The date and time the test results were saved in the memory of the tester
5. General Information to be provided in the electronic data base with the test results information for each
link:
a) The identification of the customer site as specified by the end-user
b) The identification of the link in accordance with the naming convention defined in the overall
system documentation
c) The overall Pass/Fail evaluation of the link-under-test
d) The name of the standard selected to execute the stored test results
e) The cable type and the value of NVP used for length calculations
f) The date and time the test results were saved in the memory of the tester
g) The brand name, model and serial number of the tester
h) The identification of the tester interface
i) The revision of the tester software and the revision of the test standards database in the tester
j) The test results information must contain information on each of the required test parameters that
are listed in Section I.B and as further detailed below under paragraph I.C.6.
6. The detailed test results data to be provided in the electronic database for each tested link must contain
the following information (only one of these two formats must be specified):
a) For each of the frequency-dependent test parameters, the value measured at every frequency during the test is stored. In this case, the PC-resident database program must be able to process the stored results to display and print a color graph of the measured parameters. The PC-resident software must also provide a summary numeric format in which some critical information is provided numerically as defined by the summary results (minimum numeric test results documentation) as outlined above for each of the test parameters.
Length: Identify the wire-pair with the shortest electrical length, the value of the length rounded to the nearest 0.5 m [optional: foot] and the test limit value
Propagation delay: Identify the pair with the shortest propagation delay, the value measured in nanoseconds (ns) and the test limit value
Delay Skew: Identify the pair with the largest value for delay skew, the value calculated in
nanoseconds (ns) and the test limit value
Attenuation: Minimum test results documentation as explained in Section I.B for the worst pair
Return Loss: Minimum test results documentation as explained in Section I.B for the worst pair as measured from each end of the link
NEXT, ELFEXT, ACR: Minimum test results documentation as explained in Section I.B for the worst pair combination as measured from each end of the link
PSNEXT, PSELFEXT, and PSACR: Minimum test results documentation as explained in Section I.B for the worst pair as measured from each end of the link
b) For each of the frequency-dependent test parameters, the minimum test results documentation shall be stored for each wire-pair or wire-pair combination as observed from each end of the link. The minimum test results documentation for each test parameter shall be in compliance with the information in Section I.B.
Link length, propagation delay, and delay skew shall be reported for each wire pair as well as the test limit for each of these parameters.
六类布线标准的意义及对布线安装的影响
 
  二○○二年六月十七日,TIA/EIA委员会正式发布综合布线六类标准,作为TIA568B的补充TIA568B.2.1,TIA568B从此真正成为一个能够全面满足目前的网络发展状况解决网络建设的基础标准集。尽管网络的发展日新月异,但就网络建设来说,千兆网络即将成为网络建设的普遍需求时,作为网络的骨架,六类标准的推出可以说是"及时雨",为建设基于千兆以太网的企业新一代网络在物理层打下了坚实的基础。
  Cat6双绞线布线标准的正式推出,对布线厂商、系统集成商、测试服务提供商及用户都有非常重大的意义。对于布线厂商们来说,六类正式标准的发布让大家少了一些争议。自从六类布线系统正式进入市场,布线厂商纷纷推出自己的Cat6布线系统,而对于六类标准的争议不断见诸报端,大家仁者见仁,智者见智,不断将自己在六类布线产品上的先进技术与理念传递给大家,为布线标准的发展和制订做出了积极的贡献。但各厂商的线缆、连接器的技术参数互不兼容,测试的适配器和测试标准更是五花八门、各有千秋。在一些招标项目中由于标准的不统一,人为造成了许多暗箱操作的机会。即使在公开公正的招投标项目中中标,依然免不了被人置疑。正是因为没有一个正式的、统一的标准,才造成了布线市场如此的不统一与不和谐。一个正式的标准,可以起到大浪淘沙的作用,把布线行业中不规范的市场行为降到最低。
  对于集成商来说,六类标准的推出,给了集成商一个新的机会。尽管网络集成行业仍然是一个朝阳行业,但越来越透明的价格,越来越低的利润,越来越残酷的竞争使大部分普及型的网络建设早已无利可图,而高端应用的集成虽然能够获取应得的利润,但其对产品、技术的要求和用户的认知度有更高的要求,一个没有正式标准的系统如何让用户接受也是一个非常艰难的工作,更不用说各种将来未知的服务了。一个正式的标准令集成商们松了一口气,再也不用为向用户解释草案标准而苦恼了。
  对于用户来说,六类正式标准的推出吹散了大家心中的迷茫,自从六类布线系统正式出现在市场上,无数不满足于五类、超五类布线系统的用户,希望能够应用六类系统,以满足千兆网络的需求,而四年来的各种六类草案却令许多用户望而却步,网络技术的飞速发展让任何一种技术都不敢在正式的标准出来之前而成为主流,就象当年的100VGAnyLan一样,当先进的技术不能成为主流产品时,必然被淘汰,非主流产品即无法得到产品技术的升级保证,更无法保证自己的投资。尽管TIA568B标准属于美洲标准,但在网络建设维护方面无论是技术还是理念都以美洲标准为依据的亚洲来说,这个标准能够满足90%以上的中国用户的需求。追求品质的用户不再犹豫,他们不需要再面对各种标准草案、各种六类技术而无法抉择,他们只要问一句能否通过TIA六类标准的测试,Draft标准之间的区别与我何干。
  对于一个新建设的布线系统来说,现场认证测试是一个最重要的环节,它将确认这个布线系统能否提供设计上的性能要求,所以正式标准中的现场测试指标就更为重要。对于安恒公司这样的长期专注于布线现场测试技术和服务的公司来说,没有一个正式的标准作为依据是测试时遇到的最大问题,尽管用户并不理解为什么有了六类产品,而测试却只能用草案标准,即使测试人员向用户解释六类草案几乎是当时最先进的测试标准,但他们依然对不同的厂商使用不同的标准表示质疑,直到美国福禄克网络公司正式推出永久链路适配器的布线测试解决方案,才使这一矛盾有所缓解。尽管目前六类布线系统的测试依然有厂商之分,但永久链路测试适配器的推出已经满足了大部分厂商的兼容性问题。六类正式标准的发布让测试服务人员面对用户时少了许多尴尬与难堪。 六类正式标准的推出,用户将不再犹豫,六类布线系统建设会更多。六类正式标准的推出也打消了一些劣质产品的以次充好的机会,合格的、符合标准的六类布线系统也会更多;六类正式标准的推出也会给安恒公司这样专业的测试服务公司带来新的机会与发展,重要的是六类正式标准的推出会使国内网络建设的发展和应用产生一个新的增长点。路宽了,好车还会少吗?
  
 
六布线标准,综合布线标准,网络标准,六类系统,六类综合布线系统标准,综合布线,六类线标准,企业系统集成六类布线标准,综合布线标准,网络标准,六类系统,六类综合布线系统标准,综合布线,六类线标准,企业系统集成六类布线标准,综合布线标准,网络标准,六类系统,六类综合布线系统标准,综合布线,六类线标准,企业系统集成六类布线标准,综合布线标准,网络标准,六类系统,六类综合布线系统标准,综合布线,六类线标准,企业系统集成类
六类布线标准
 
 
六类布线标准正式颁布
布线标准变化的原因
六类布线标准颁布的意义
六类布线标准
制定标准的组织
常用国际布线标准

联系方式:021-51098989 E-mail:sh@f-net.com.cn

上海慧锦光电线缆集团信息中心》制作 版权所有

© 2000-2001 All Rights Reserved